New Erving Public Library

Library Building Project & Library Building Committee
  • New Erving Public Library
    Walls going up! More »
  • Floor Plan
    Floor Plan

Project History

The project was substantially completed at the end of February 2020 and opened to the public on March 1, 2020 until March 12, 2020. Due to Covaid-19, the Library was closed for the remainder of March and beyond.  A grand opening is still in the planning. 

Review construction here

This is a project funded by the Commonwealth of Massachusetts through the Massachusetts Board of Library Commissioners and the town of Erving and other fundraising efforts. The project is 8,294 sq. ft. of new construction. 

Planning for a new library began in 2010. The project manager and the architect were hired in 2013. The planning phase was completed in January 2017 and a grant application for $2.7 million was submitted by Library Director, Barbara Friedman and granted in February of 2018. 

This building was designed by Johnson Roberts Associates. The chief architect for this project is Philip O'Brien. Erving's project managers are Daniel Pallotta and Robert Todisco of P3, Inc. They represent the town during all phases of the project from planning until after completion. Nick Jablonski will serve as the Clerk of the Works. Marois Construction was granted the contract in March of 2019. Jeff Bouyea represents the company onsite.

The Library Director and Erving residents have been actively involved in the planning process since 2013. A successful planning grant allowed the Feasibility Committee to hire the architect and project manager and consider three possible locations for the library. Residents who served for three years on that Committee were: Jacquie Boyden, Rebecca Hubbard, Elaine Stafford, Michele Turner and Dennis Wonsey.

In 2016, another citizen's advisory committee was formed, the Library Building Committee, which includes Barbara Friedman, Library Director and Erving residents: Marcia Bernard, Jacquie Boyden, Sara Campbell, Rebecca Hubbard, Cynthia and Rupert Roy-Clark, Deb Smith and Charles Zilinski, 

Please refer questions to [email protected]

 — in Erving, Massachusetts.

Building Project Timeline


Project Partners

Owner's Project Manager
P-Three, Inc
Designer/Architect
Johnson Roberts Associates, Inc.

General Contractor

Marois Construction

 

Staff Contacts

Name Title Phone
Barbara Friedman Library Director (413) 423-3348

Library Building Committee Members

Name Title
Sara Campbell Co-Chair
Jacquelyn M. Boyden Co-Chair
Jacquelyn M. Boyden
Rebecca Hubbard Member
Debra Smith Member
Charles Zilinski Member