Work in several areas of Town is scheduled to begin this month. Please note the below construction timelines which may affect traffic patterns.

Papermill Road - Force Sewer Main

Monday September 27 - Friday October 1: Papermill Road will be closed. The detour will direct vehicles onto Lester Street and Prospect Street to connect with Route 2. 

Ervingside Sidewalk Improvements

Sidewalk and crosswalk improvement work will tentatively begin Monday September 27 on Central Street & Park Street. Once work in this neighborhood is substantially completed, the crews will move on to Pratt Street & Gunn Street. The work in this neighborhood is expected to begin in mid-October. A police detail will be scheduled for the work on Pratt Street.